Commissioning: making your buildings perform, from project to operation
A commercial building handed over with no defects can consume 50% to 100% more than planned three years after delivery. Everyone signed, nobody tested. Commissioning tackles that gap phase by phase: a commissioning process follows the project from design through to operation and checks that the energy performance promised shows up in the operating costs. Otherwise the design team specifies, the contractor delivers, and nobody looks.
Understanding commissioning and its different approaches
What commissioning means
Commissioning, or Cx, is a quality process applied to a building's technical installations. You do not note that a piece of equipment is installed: you run it and record what it actually does, against what the brief asked for.
The commissioning process covers HVAC (heating, ventilation and air conditioning), the BMS and the building's technical packages. Administrative handover, by contrast, checks that there is a signature at the bottom of a certificate. A BMS can be handed over with no defects listed and still be full of them, because nobody tested it.
What a commissioning process sets out to do
Three objectives :
- Contractual compliance : what was delivered matches what the specification asked for.
- Real energy performance : making sure the building reaches the consumption level announced at design stage, not only in simulation.
- Quality of operation: making sure the control sequences do what they should with occupants inside, on a Monday in January, not only on the test bench.
Initial commissioning on a new installation
On a construction project or a major refurbishment, commissioning starts at the briefing stage, not at handover. The agent reviews the control sequences on paper, sets the acceptance criteria, follows the site and tests every new installation at start-up. A fault found on paper costs one meeting; found after delivery, it costs rework, a variation order and often two years of excess consumption.
Retro-commissioning on an existing building
Commissioning: the numbers that matter
These savings come mainly from correcting the gaps between the control sequences as programmed and how the equipment actually behaves: valves that do not close fully, badly calibrated sensors, unsuitable start-up schedules. Commissioning identifies and corrects this drift, which is usually invisible in day-to-day operation.
The cost of commissioning generally represents 1 to 3% of the total cost of an HVAC project for a new building, and stays marginal against the savings generated over the building's life. In retro-commissioning (existing building), the investment pays back faster still, because the anomalies are usually numerous.
That gap, sometimes called the performance gap, comes from several factors: unsuitable default settings, sensors left uncalibrated after installation, incomplete control sequences, or simply no functional testing of the BMS automation before delivery.
Part 2 of the standard (EN 16247-2) covers buildings specifically (part 3 covers industrial processes and part 4 transport). It does not define commissioning but complements it: it can serve as the methodological framework for the audits that precede retro-commissioning.
Retro-commissioning addresses buildings in operation where nobody knows any more what the BMS is doing. The survey asks simple questions: which setpoints are actually applied, how many overrides are active, what the history says. Nine BMS installations out of ten are shaky, and it shows as soon as you open the cabinet. The action plan first corrects whatever weighs most on operating costs.
The three approaches compared
The three approaches compared
Initial commissioning, retro-commissioning and continuous control
| Criterion | Initial commissioning | Retro-commissioning Recommended entry point | Continuous control |
|---|---|---|---|
| Scope | New build or major refurbishment | Existing building in operation | Building already commissioned or made reliable |
| When it happens | From the briefing stage onwards | At any time on a site in operation | After the BMS has been made reliable |
| Typical cost | 1% to 3% of the works budget | 1% to 3% of the corrective works budget | Annual subscription (varies with floor area) |
| Expected gains | Prevention of post-handover overruns | Rapid reduction in operating costs | Continuous optimisation over the building's life |
| Length of the assignment | The whole project (12 to 36 months) | 3 to 6 months (audit + action plan) | Multi-year commitment |
| Main parties | Cx agent, design team, contractors | Cx agent, operator, client | Operator, control provider |
| Regulatory link | Décret tertiaire + BACS decree (new-build obligations) | Décret tertiaire (evidence of reduction) + ADEME funding | Décret tertiaire (tracking targets over time) |
Cost source: Akéa Énergies - Cx = commissioning
Each type of commissioning matches a moment in the building's life; the table above guides the choice. An assignment costs between 1% and 3% of the works budget (source: Akéa Énergies).
On an existing portfolio, retro-commissioning is the first step: no building works, and operating costs fall as soon as setpoints and schedules become coherent again, because energy in commercial buildings is wasted mostly outside occupancy. Continuous control, by contrast, assumes a BMS that has already been made reliable: optimising a system nobody understands is like fine-tuning the heating curve of a boiler whose three-way valve nobody has checked.
The parties involved and the commissioning plan
The commissioning agent: role and independence
The key parties in commissioning
Click each party to see their role and responsibilities in the Cx process
Commissioning (Cx) brings together a multidisciplinary team. Each party steps in at specific phases to secure the building's real performance.
Sources: ASHRAE Guideline 0-2019, NF EN ISO 16484, COSTIC commissioning guide 2023
The commissioning agent is a third party. Their commissioning assignment comes down to three verbs: check that what is installed matches the specification, test how it actually runs, document every gap in a report that can be held up in a dispute.
Their independence from the design team and from the BMS integrator is what makes the findings credible. You cannot be both the person who programmed the sequences and the person who signs to say they work. Nobody doubts the integrator's honesty. Their position, yes.
Advisory and commissioning: what is the difference?
BMS Advisory helps the client decide: frame the need, write the brief, challenge a quotation. The commissioning assignment checks that the decision was carried out correctly.
The design team designs and directs the works; the agent checks the result. In our experience the two hats often sit on the same head: an advisor who wrote the specification is well placed to check it was followed, provided they sell nothing afterwards.
The client and the information asymmetry
Commissioning: the mistakes that wreck your performance
Commissioning is not simply start-up: it is the systematic verification that each technical package works as the design intended. Without that rigour you inherit installations consuming 15 to 30% more than planned, sometimes for years, without anyone noticing. The point is not to tick boxes but to secure real performance from the day the building is delivered.
The commissioning agent must step in from the briefing stage, not at handover. That is where the performance requirements (OPR) and the verification criteria are set. A Cx started at the end of the site works will never make up for a design fault. Use ASHRAE Guideline 0 as the methodological reference.
A chiller running standalone proves nothing. The real test is the complete sequence : sensor signal, processing by the BMS controller, action on the valve or the drive, and verification of the result in the zone. Test the fallback modes too: what happens when a sensor fails?
A commercial building takes 10 to 12 months to go through all its operating conditions (heatwave, deep cold, varying occupancy). Plan for seasonal commissioning over 12 months minimum, with quarterly measurement points. It is the only way to validate setpoints in real conditions.
The BMS is the building's nervous system : if it is not properly configured, no technical package will deliver its rated performance. Check the setpoints, the time schedules, the alarm thresholds and the consistency between the BACnet/LonWorks protocols and supervision. A 2 °C error on a setpoint means 15% excess consumption.
To put figures on the gains from commissioning, rely on IPMVP (International Performance Measurement and Verification Protocol). It structures the measurement by defining a baseline, weather adjustments and a clear measurement boundary. Without that framework there is no way to prove a 20% gain is real rather than the result of a mild winter.
Need BMS support for your commissioning? →
Recommendations drawn from ASHRAE Guideline 0-2019 and the IPMVP protocol (EVO, 2022)
The property decision maker carries the budget and the risk, and usually decides with no in-house BMS expertise, on the advice of the people who will sell the works. When they are quoted €1m for a BMS, the person quoting is also the person who will bank it. Commissioning breaks that information asymmetry : a commissioning agent who sells nothing has only one interest, that the findings are correct.
The measurement and verification plan
The commissioning plan writes down the proof before the works start: indicators, measurement points, calculation method. Without it, the gains announced at the end are declared gains, and a declared gain is not discussed, it is disputed.
The IPMVP protocol provides the methodological framework for performance monitoring; the degree-day weather correction separates what the control system changed from what the winter did on its own. That level of rigour makes energy performance auditable by a third party and defensible.
The list of commissioning operations
Each operation targets a specific checkpoint, a long way from a paper audit. Fine-tuning happens task by task, on the installation itself:
- Functional tests on HVAC: start, stop, changeover of each item of equipment
- Verification of the BMS control sequences in the controller, not in the manual
- Check of temperature and flow setpoints zone by zone
- Test of alarms and thresholds: an alarm that does not get through does not exist
- Review of the documentation delivered: drawings, schematics, points list, backups
- Training of the operating teams on day-to-day procedures
The programme and the parties involved at each stage
The programme of a construction project says which party steps in at which phase. The client approves the objectives, the design team leads the design and the site works, the contractors build, the agent checks at every milestone and the operator takes over at handover.
That last handover is where things break most often. The operator who gets the keys rarely receives the approved sequences and the list of what was tested. They receive a password.
The stages of the process and the measurable benefits of commissioning
Design phase: build commissioning in from the briefing stage
From the design phase onwards, the agent reviews the HVAC and BMS specifications with a single question: how will we prove this works? They approve the control sequences on paper and set measurable acceptance criteria, with a figure, a tolerance and a method. What the specification does not write down will never be obtained at handover. Getting this right costs hours; getting it wrong costs variation orders.
Construction phase: site supervision and installation checks
During site supervision, the agent compares the installation against the construction drawings: hydraulic connections, controller wiring, sensor positions. A room sensor mounted above a convector is invisible once the false ceiling is closed. A gap picked up at this stage costs ten times less than after handover.
Start-up: functional tests and fine-tuning
Start-up is where the paper meets the building. The agent runs the functional tests : AHU in summer then winter mode, control loops, setpoints by zone, behaviour on fault. Fine-tuning adjusts the parameters until the system runs as specified. It is the last safeguard, and the one the delivery schedule breaks most often.
Operation: monitoring over the building's life
Commissioning does not stop at the handover certificate, even if most assignments sold do stop there. In operation, performance monitoring compares consumption against the baseline every month. Without it, the conditions that hold performance in place disappear at the first complaint or override, and operating costs climb with no alert. Tracking baselines across the building's life cycle lets you correct before the gap becomes the new normal.
The full commissioning life cycle
Commissioning life cycle
Click each phase to see the detail
- Performance objectives written down
- Scope of the assignment defined
- Commissioning budget agreed
- Client
- Commissioning agent
- BMS Advisory
- Approval of measurable acceptance criteria
Handover risk: the performance objectives are set but not translated into testable criteria. The project moves into design with no measurable reference.
- Control sequences approved on paper
- Acceptance criteria per technical package
- Commissioning plan written down
- Commissioning agent
- Design team
- HVAC design office
- Design review: are the sequences testable in real conditions?
Handover risk: the design requirements get lost between the specification and the construction drawings. The integrator interprets instead of applying.
- Installation check sheets
- Report of the gaps found
- Commissioning agent
- Contractors
- Design team
- Connections, wiring and sensor positions against the construction drawings
Handover risk: the temporary overrides put in place during the site works are still active at start-up. Nobody documents them.
- Functional test certificates
- Consumption baselines approved
- Operating documentation handed over
- Commissioning agent
- Operator
- Client
- Control sequences tested under real occupancy
Handover risk: the approved documentation never reaches the operator. The settings are overwritten by untracked interventions within the first few months.
- Quarterly monitoring reports
- Baselines compared year on year
- Ongoing corrective action plan
- Operator
- Commissioning agent
- Client
- Baselines against real consumption (IPMVP protocol, degree-day correction)
Ongoing risk: with no structured monitoring, comfort complaints handled in a hurry pile up untracked overrides. Energy drift sets in gradually.
Do you suspect drift across your commercial buildings?
Book a BMS audit →The commissioning process runs through five phases across the building's life cycle : briefing, design, site works, start-up, operation. What the timeline shows above all is that the risk sits at the handovers. Between acceptance and operation, the approved settings are overwritten by overrides nobody records. The question to ask before signing: of those five phases, how many does the quotation actually cover?
Cutting operating costs through measurable energy savings
Commissioning done properly produces energy savings from the first year, and operating costs fall accordingly. They still have to be measured: the IPMVP protocol requires a weather-corrected baseline, without which the gains stay declarative. ADEME in fact ties its funding for local authorities to 40% energy savings (source: ADEME commissioning factsheet). We do not promise that figure to a building we have not seen.
Meeting the regulations: Décret tertiaire and BACS decree
The Décret tertiaire , the French decree on energy reduction in commercial buildings, requires a progressive cut in consumption for buildings over 1,000 m²; commissioning provides the evidence of those cuts in operation. The BACS decree (building automation and control system, decree no. 2020-887) requires automation and control functions: sites above 290 kW have had to comply since 1 January 2025, and the deadline for the 70-290 kW band was pushed back to 1 January 2030 by decree no. 2025-1343 (source: Légifrance). A BMS that complies with the decree and has never been tested is still a BMS that over-consumes.
Obtaining and keeping certifications: HQE and environmental labels
HQE certification calls for evidence on the energy and comfort targets; commissioning supplies it: measurements in real conditions, approved sequences, post-handover monitoring. But a label is a photograph, not a performance. We have seen certified buildings tick every box at delivery and over-consume three years later.
Preventing energy drift after handover
The performance gap between planned and real consumption can reach 50% to 100% in a commercial building in operation (source: professional literature, COSTIC commissioning handbook). The causes are mundane: overrides put in place to calm a complaint and never removed, design documentation lost at the first change of operator, a setpoint pushed to 24 °C for the director on the top floor (seen many times). Putting structured monitoring in place, with baselines compared and alerts on the gaps, stops that energy drift.
Budget and return on investment
An assignment costs between 1% and 3% of the works budget (source: Akéa Énergies). The return on investment is calculated against the operating costs avoided over five to ten years. On a large commercial site, commissioning pays for itself in one to three years. On a small building, the payback can stretch considerably: the absolute gains stay modest and the payback period becomes hard to defend. Every company has to run that calculation on its own portfolio, with its own history, not with a range.
ADEME funding for local authorities
Commissioning: what ADEME says
Sources: ADEME, "Commissionnement des bâtiments tertiaires" guide, 2024 - ADEME/CEREMA operational feedback
ADEME co-funds commissioning assignments for local authorities, covering the study and monitoring costs. The scheme assumes a costed action plan and a documented savings target.
The 10 questions to ask before signing an assignment
10 questions before signing an assignment
Tick each point you have checked - click ⚠ to see the warning signs
Are you preparing a tender or a BMS assignment?
Book a BMS audit with an independent agent →Before signing a commissioning assignment, the client needs concrete criteria, because commercial proposals rarely spell out what matters: real scope, deliverables, measurement protocol. In practice the most useful assignments are those whose commissioning plan also covers operation and the handover to the teams in place. The others stop at the handover certificate, exactly when the problems start.
The checklist above covers four themes: technical scope, deliverables, success indicators and continuity after the defects liability period. Each question comes with its warning sign. An assignment whose overall delivery is not framed at this stage ends up as a PDF report nobody reads again.
Foobot: from commissioning to continuous energy control
BMS Advisory: make the BMS reliable before optimising it
A BMS that has never been audited cannot be optimised. Our BMS Advisory starts with a survey that pulls no punches: active overrides , meter reliability where readings are inconsistent, sequences put back in order, maintenance contract reviewed. It is the field equivalent of retro-commissioning, with our own tools for testing the points. That reliability work stands on its own: there is not necessarily an AI layer behind it. AI control only comes in if the building lends itself to it.
AI Control: extending the gains from commissioning with a digital twin
Once the BMS is reliable, AI Control extends the gains from commissioning over time. A digital twin is trained on the BMS history, the weather and occupancy; predictive control rewrites the HVAC setpoints every 15 minutes through the existing BMS, with no building works.
Measured result at Valeo: −28.6% HVAC consumption, verified under the IPMVP protocol with degree-day weather correction. Performance monitoring stays continuous and auditable by a third party, the only honest way to announce an energy performance figure.
Optimal Start: optimising start-up zone by zone
Optimal Start recalculates the heating start time every day, zone by zone, from thermal inertia, the weather and real occupancy. Predictive optimal start replaces the conventional optimiser, whose logic has not moved in 25 years: a single start time for the whole building.
It runs on the existing BMS. With start-up by zone, occupants arrive in spaces that are up to temperature, without having heated empty floors.
FAQ - Commissioning
What is commissioning?
Commissioning is a structured process for verifying a building's technical installations. It covers HVAC and the BMS from design through to operation. The commissioning process makes sure each system does what it was bought to do.
How do you set up commissioning?
It starts with a commissioning plan written before the works: scope, milestones, test and measurement protocols. The commissioning assignment goes to an agent independent of the design team, from the briefing stage onwards.
What are the benefits of commissioning?
Commissioning cuts operating costs by correcting faults before they settle in. It makes real energy performance verifiable and produces measurable energy savings from the first year.
What are the stages of commissioning?
Five stages across the building's life cycle: design phase, site supervision, start-up, operation and multi-year monitoring. Each phase produces deliverables a third party can verify.
Who can carry out commissioning?
The commissioning agent is a third party independent of the design team and of the integrator, which is what makes the findings objective. The assignment can also be carried by a BMS advisor, provided they do not sell what they verify.
What does commissioning cost?
Commissioning represents 1% to 3% of the works budget. That budget pays for itself through lower operating costs across the building's life cycle. The payback depends on the size of the site.
How do you guarantee a building's planned energy consumption?
Commissioning extended by continuous performance monitoring is the only way to hold an energy target over time. The IPMVP protocol structures the measurement of gains with degree-day weather correction; the results are auditable by a third party.
What is the difference between commissioning and retro-commissioning?
Commissioning applies from the design of a new installation. Retro-commissioning targets an existing building whose performance has drifted, starting from a survey of the BMS. Same method: test, measure, document.
How does commissioning relate to HQE certification?
Commissioning supplies the technical evidence HQE certification requires: measurements in real conditions and documentation of the approved sequences. It makes an environmental certification easier to obtain and, above all, easier to keep.
