Large UK undertakings have until 5 December 2027 to notify compliance with Phase 4 of ESOS, the Energy Savings Opportunity Scheme. One route is a certified energy management system (EnMS) to ISO 50001 covering total or significant energy consumption, energy measurement plan included[1][1]RegulationGOV.UK, “How to comply with the Energy Savings Opportunity Scheme (ESOS) Phase 4”, guidance published 30 July 2026 (qualification date 31 December 2026, compliance deadline 5 December 2027, ISO 50001 route) | https://www.gov.uk/government/publications/comply-with-the-energy-savings-opportunity-scheme-esos-phase-4/how-to-comply-with-the-energy-savings-opportunity-scheme-esos-phase-4See in sources ↓. The metering plan, another name for the same document, sets out which energy consumption to measure, where and how. On most sites, meters and a building management system (BMS) are already in place, but their data has never been tested. Here is the BS EN 17267 method applied to the meters you already have.
What is an energy measurement plan and which standards govern it?
What an energy measurement plan sets: what to measure, where, how often and how accurately
An energy measurement plan, or metering plan, is the document that organises a site's measurement system. It specifies which uses to track, with which measuring instruments, at which point of the distribution, how often and how accurately.
In ISO 50001, this energy metering feeds the energy performance indicators (EnPIs) and the consumption tracking of the EnMS. Each measurement must serve a named objective; otherwise the energy performance you report remains an estimate.
Metering plan, measurement plan and energy data collection plan: one and the same thing
Four labels describe the same thing. Operators talk about a metering plan. BS EN 17267 talks about an energy measurement and monitoring plan[2][2]Standards and protocolsBSI, “BS EN 17267 Energy measurement and monitoring plan. Design and implementation. Principles for energy data collection”, 2019, voluntary standard in forceSee in sources ↓. ISO 50001 requires an energy data collection plan, which many call the ISO 50001 metering plan.
From one label to the next, only the framework that requires it changes: a voluntary management approach, a certified management system or a legal obligation. The energy metering plan remains the same document.
Objectives and benefits: from the energy bill to the supply point, then to each use
The plan works down from the energy bill to the supply point (the meter point behind your MPAN or MPRN), then to each use.
The order matters: indicator priorities come before the choice of meters. This informed choice avoids metering a circuit that nobody will ever analyse.
The benefits follow: energy monitoring makes drift visible, which makes cost reduction quantifiable. The same measurements give an ESOS assessment real data and feed the total kWh that SECR reporting puts in the directors' report.
BS EN 17267: a voluntary method standard
BS EN 17267 describes the design and implementation of an energy measurement and monitoring plan[2][2]Standards and protocolsBSI, “BS EN 17267 Energy measurement and monitoring plan. Design and implementation. Principles for energy data collection”, 2019, voluntary standard in forceSee in sources ↓. It devotes a chapter to the steps of the plan and an annex to the metrological maintenance of meters[2][2]Standards and protocolsBSI, “BS EN 17267 Energy measurement and monitoring plan. Design and implementation. Principles for energy data collection”, 2019, voluntary standard in forceSee in sources ↓. The plan must take into account the factors that influence each consumption: weather, occupancy, type of production. Being voluntary, it serves as a reference tool without amounting to regulatory compliance.
It breaks the approach down into six steps: set the context and objectives, assess the initial situation, build an action plan, then implementation, operation and maintenance[2][2]Standards and protocolsBSI, “BS EN 17267 Energy measurement and monitoring plan. Design and implementation. Principles for energy data collection”, 2019, voluntary standard in forceSee in sources ↓.
What must an energy measurement plan contain for an ISO 50001 audit?
An ISO 50001 certification auditor opens the data collection plan first. They look for data on significant energy uses (SEUs) and their relevant variables.
EnPIs must relate to the energy baseline (EnB). The auditor also checks the accuracy and repeatability of each measuring device. For the ESOS route, the certificate must be issued by an accredited certification body (UKAS in the UK) and be valid on 5 December 2027; the current edition is BS EN ISO 50001:2018+A1:2024[1][1]RegulationGOV.UK, “How to comply with the Energy Savings Opportunity Scheme (ESOS) Phase 4”, guidance published 30 July 2026 (qualification date 31 December 2026, compliance deadline 5 December 2027, ISO 50001 route) | https://www.gov.uk/government/publications/comply-with-the-energy-savings-opportunity-scheme-esos-phase-4/how-to-comply-with-the-energy-savings-opportunity-scheme-esos-phase-4See in sources ↓.
Finally, they ask who owns the plan: energy lead, energy manager or energy team.
The 6 steps of BS EN 17267, starting from the meters you already have
Step 1: define the context, objectives, constraints and energy team
The first step is to define the context: who owns the plan, what the measurements will be used for, which uses to cover. An energy lead or an energy manager runs it, with an energy team that involves operations.
SEUs come from the energy review: you do not redo it. In industry, flow mapping adds compressed air and gas. In commercial buildings, hot water and cooling dominate. Short training for the operators is essential, since they are the ones who will read the meters.
Step 2: assess the initial situation from what your meters and BMS already measure
Assessing the initial situation starts with what already exists. Main meters, heating, ventilation and air conditioning (HVAC) or process sub-meters, BMS sensors: a site often has dozens of them. Our position fits in one sentence: a meter that reports to the supervision system is not a reliable meter.
In England, Approved Document L requires a building automation and control system in new non-domestic buildings whose heating or air-conditioning output exceeds 180 kW, and a system installed or replaced in such an existing building must continuously monitor, log and analyse energy use[3][3]Building regulationsHM Government, Approved Document L, Volume 2: Buildings other than dwellings, 2021 edition incorporating 2023 amendments, paragraphs 6.66 to 6.73 (building automation and control systems)See in sources ↓. On those sites much of the data already exists, untested. To carry out this inventory, here are the nine questions to ask your O&M contractor. Each comes with the test that settles it.
What your meters and BMS already measure, and what to test before buying a meter
Nine questions to ask your O&M contractor, each followed by its test. Valid for a commercial building as well as an industrial site.An unanswered point is tested before it is replaced. The boxes left empty form the to-do list of the action plan: they say what to test, not yet what to buy. This current-state review extends the work described in our article ISO 50001 and BMS.
Step 3: install new meters or use the ones you have?
Indicators come before meters. A meter is installed only if an EnPI or an SEU requires it and no existing point serves it. Pricing comes after the current-state review, never before.
A new meter installed with no indicator to serve is an expense, not a measurement.
The metering techniques available change nothing in this order. The action plan lists the missing points, the indicator they serve and the need they meet. Every future improvement action depends on it. The aim remains to get it right from the first iteration, with no work to redo at the first audit.
Step 4: put the measuring instruments and data collection in place
Implementing a plan follows the energy carriers. Electricity, natural gas, thermal energy and compressed air each have their own measuring instruments and metering techniques.
The connection goes through the supervision system or a multi-protocol controller, via the building communication protocols BACnet or LonWorks (often shortened to LON). A single plan template lists every point in one table, whatever its protocol; where Approved Document L applies, the BACS must also be interoperable with other systems[3][3]Building regulationsHM Government, Approved Document L, Volume 2: Buildings other than dwellings, 2021 edition incorporating 2023 amendments, paragraphs 6.66 to 6.73 (building automation and control systems)See in sources ↓. Energy management software completes the set-up. Before any purchase, an audit of the existing installation pinpoints only the points that are genuinely missing.
With this audit, each line of the purchase order matches a gap found during the inventory. The data collected can then feed the indicators.
Step 5: use the measurements to track EnPIs and consumption
Measurement for monitoring turns data into EnPIs, then EnPIs into decisions. Raw consumption says nothing. Related to production, to heating degree days (HDD) or to occupancy, it becomes an indicator.
Consumption tracking then compares each EnPI with its baseline and flags the gap. To build these energy performance indicators, one rule holds: measure the efficiency of a use, not the activity of a meter.
Step 6: maintain the measurement system and data quality
An energy measurement plan degrades silently. To maintain the system, operations and maintenance check the meters, remove useless alarms and keep those that flag a frozen value.
A periodic review of the plan holds the points up against actual uses. Staff change, and so does equipment: data quality keeps up or falls behind with them. One question remains that maintenance alone does not settle: what your meters really measure.
Accuracy and reliability: what your meters really measure
What measurement accuracy should you aim for, depending on how the figure is used?
Measurement accuracy is chosen according to how the figure will be used. Recharging a cost to a tenant requires accuracy comparable to that of the supply point, and therefore of the energy bill. Tracking an EnPI tolerates a gap, provided it stays stable. Verifying a saving requires measuring instruments whose uncertainty stays below the expected saving. The time step follows the same logic: real time serves control, rarely reporting.
How do you check that a meter measures correctly?
Five tests are enough to separate reliable meters from the rest:
- Reconciliation of the bill against the sum of the sub-meters
- Comparison of readings between the supervision system and the meter on site
- Check of the transformer ratios entered
- Metrological verification of the meters used for recharging
- Cross-check with a second sensor on the same fluid
From the energy measurement plan to the measurement and verification plan
What the EnB must contain to serve one day as the baseline for a saving
The energy baseline is not only for ISO 50001. It will become the baseline for any saving to be demonstrated, including in an energy performance contract (EnPC). It fixes a complete baseline period and the influencing factors of energy consumption: degree days, occupancy, production. Without them, no value measured later can be compared.
Degree-day weather correction: do not mistake a mild winter for a saving
Degree-day weather correction brings heating consumption back to a reference climate. Heating degree days add up, day after day, the gap between a base temperature (15.5 °C is the usual base in the UK) and the mean outdoor temperature. A mild winter lowers the bill without energy efficiency having moved at all.
A mild winter is not a saving.
Occupancy and production are normalised in the same way. Without these factors, tracking energy performance amounts to judging a building on the weather.
Make the data reliable first, then control: what Foobot brings to your energy measurement plan
Meter reliability: the critical inventory of BMS advisory
Our BMS advisory starts with a current-state review of the existing metering plan, meter by meter. No building works here: we correct links, units and BMS parameters.
The Meter reliability deliverable tracks down disconnections, data gaps, duplicates, invisible drift and the spikes described in the table of seven defects. It stands on its own, with no AI phase behind it. The energy lead gains a basis they can defend in an audit.
AI Control: savings measured under the IPMVP protocol, Valeo at -28.6% on HVAC
Once the data is reliable, AI Control only comes in if the complexity of the building justifies it. A digital twin trained on BMS histories controls the HVAC every 15 minutes, 24/7, with no building works.
At Valeo, the saving reached -28.6% of HVAC consumption, measured under the IPMVP protocol with degree-day correction. A figure like that only holds on a baseline built from tested meters.
The free Foobot EMS to track your consumption right now
The free Foobot EMS is an energy monitoring tool centred on the inventory of meters and measurement points. Where a building is covered by Approved Document L, its BACS already logs and analyses energy use continuously[3][3]Building regulationsHM Government, Approved Document L, Volume 2: Buildings other than dwellings, 2021 edition incorporating 2023 amendments, paragraphs 6.66 to 6.73 (building automation and control systems)See in sources ↓: those points go into the inventory first. The EMS serves the first task of consumption tracking: listing what is already metered and linking each point to a use.
Energy measurement plan: before the first new meter, inventory what exists
An energy measurement plan starts from what is already metered. Data reliability comes before buying any new meter. An EnB built on tested points prepares the proof of savings starting today.
Your next step: export one week of history from your energy meters, compare it with the bill and spot the gaps. The IPMVP protocol will then tell you how to turn this metering into proof. The free Foobot EMS handles the inventory of meters and measurement points. If you would like an engineer to open your histories with you, let's talk.
FAQ - energy measurement plan
Metering plan vs measurement plan: are they the same thing?
Yes. Metering plan, measurement plan and energy data collection plan describe the same thing: what to measure, where, at what time step and how accurately. Only the framework that requires it changes, ISO 50001 or BS EN 17267[2][2]Standards and protocolsBSI, “BS EN 17267 Energy measurement and monitoring plan. Design and implementation. Principles for energy data collection”, 2019, voluntary standard in forceSee in sources ↓.
Is BS EN 17267 mandatory?
No. It is a voluntary standard and a methodological reference tool[2][2]Standards and protocolsBSI, “BS EN 17267 Energy measurement and monitoring plan. Design and implementation. Principles for energy data collection”, 2019, voluntary standard in forceSee in sources ↓. Regulatory compliance runs through ESOS, SECR or, for new buildings above 180 kW of heating or cooling output, Approved Document L. Following the standard does, however, make the audit of an ISO 50001-certified EnMS easier.
What budget should you plan for?
The budget is costed after a current-state review of what exists. On top of the price of a meter come installation, cabling and integration into the supervision system. Test what already measures first: some of the planned meters become unnecessary.
Should you measure every 15 minutes, every hour or every day?
It all depends on how the figure is used. The 15-minute step is the benchmark for control and fault detection, as close to real time as possible. Measurement for tracking a monthly EnPI is often satisfied with an hourly or daily step.
How do you include influencing factors (weather, production, occupancy)?
Identify them when setting the energy baseline, then trend-log them at the same time step as consumption. Degree-day weather correction handles the weather. Occupancy and production come in as influencing factors in the calculation of each EnPI.
How do you draw up an energy measurement plan?
Follow the six steps of the plan described by BS EN 17267[2][2]Standards and protocolsBSI, “BS EN 17267 Energy measurement and monitoring plan. Design and implementation. Principles for energy data collection”, 2019, voluntary standard in forceSee in sources ↓. The first step sets context and objectives. Assessing the existing situation comes next: inventory the meters in place and test their reliability before buying more.
What are the benefits of an energy measurement plan?
Consumption tracking by use, cost reduction targeted at the real cost items and demonstrable energy savings. Above all, the plan provides the proof of savings: a reliable EnB makes every result verifiable by a third party.
Sources and references
3 sources.- [1]GOV.UK, “How to comply with the Energy Savings Opportunity Scheme (ESOS) Phase 4”, guidance published 30 July 2026 (qualification date 31 December 2026, compliance deadline 5 December 2027, ISO 50001 route) | https://www.gov.uk/government/publications/comply-with-the-energy-savings-opportunity-scheme-esos-phase-4/how-to-comply-with-the-energy-savings-opportunity-scheme-esos-phase-4↑ 1 2